Skip to content

Read the source behind every number.

Each citation carries its scope and limits, so readers can judge what the source supports. Primary records come first whenever they are available.

A Administrative data, audited record, permit, or rule

B Official estimate, review, or disclosed model

C Forecast or transparent working analysis

Showing 18 of 68 matching sources (68 total in the library)

  1. Official reportEvidence grade BReviewed September 24, 2026
    Jetson Orin Nano Super developer kit specifications

    NVIDIA

    Scope
    One Jetson Orin Nano Super: memory, advertised compute and module power modes
    Limitation
    Manufacturer specifications, not independent application benchmarks. Module power excludes the complete system and power-supply losses.
  2. Official reportEvidence grade BReviewed September 24, 2026
    Jetson Orin Nano Super performance and precision

    NVIDIA

    Scope
    Sparse and dense INT8 throughput for Jetson Orin Nano Super
    Limitation
    Peak throughput depends on precision and sparsity; TOPS does not measure model quality or finished requests per second.
  3. Official reportEvidence grade BReviewed September 24, 2026
    GB200 NVL72 specifications

    NVIDIA

    Scope
    One liquid-cooled rack: 72 GPUs, GPU memory and NVLink interconnect
    Limitation
    Manufacturer system specifications. Aggregated GPU memory is distributed across connected GPUs; it is not one device memory chip.
  4. Official reportEvidence grade BReviewed September 24, 2026
    GB200 NVL72 rack power and cooling FAQ

    NVIDIA

    Scope
    Approximately 120 kW at full load including rack nodes and components
    Limitation
    Rack power is not total facility power and is not directly comparable to a Jetson module power mode.
  5. Official reportEvidence grade BReviewed September 24, 2026
    Kimi K3 model card

    Moonshot AI

    Scope
    Kimi K3: 2.8 trillion total parameters; 104 billion activated per token
    Limitation
    Published model architecture, not independent performance verification. Weight storage is a lower-bound calculation, not a complete hardware budget.
  6. Official reportEvidence grade BReviewed September 24, 2026
    Gemma 3n model card

    Google

    Scope
    Small models intended for low-resource devices; training hardware and limitations
    Limitation
    On-device inference does not imply on-device original training. Model capabilities and deployment requirements vary.
  7. Official reportEvidence grade BMarch 2025
    Gemma 3 technical report

    Google DeepMind

    Scope
    Gemma 3 training, knowledge distillation and model family
    Limitation
    A disclosed example of making smaller models, not proof that every edge model uses the same training process.
  8. GuidanceEvidence grade BReviewed September 24, 2026
    Cooling water efficiency opportunities for federal data centers

    U.S. Department of Energy

    Scope
    Heat removal, cooling loops and water efficiency in data centers
    Limitation
    A liquid cooling loop does not by itself establish evaporative water consumption or a particular campus water budget.
  9. Official reportEvidence grade BFebruary 2020
    Recalibrating global data center energy-use estimates

    Masanet et al. / Lawrence Berkeley National Laboratory

    Scope
    Global modeled data-center compute instances and electricity, 2010-2018
    Limitation
    Historical modeled estimates, not a controlled test of efficiency-induced demand or a forecast for AI.
  10. Official reportEvidence grade A2025 financial year
    2025 Form 10-K: property and equipment

    Meta

    Scope
    Company accounting useful lives for servers, network assets and buildings
    Limitation
    Depreciation assumptions are neither mandatory replacement schedules nor guarantees of physical or economic life.
  11. Official reportEvidence grade A2025 financial year
    2025 Form 10-K: property, impairment and retirement obligations

    Equinix

    Scope
    One operator portfolio; facility impairment, asset lives and restoration obligations
    Limitation
    Company-specific evidence that sites can underperform. It does not estimate Peosta vacancy risk or guarantee reuse.
  12. RegulationEvidence grade AAdopted April 8, 2026
    Data Center Ordinance, section 83-18: decommissioning

    East Manchester Township, Pennsylvania

    Scope
    Local decommissioning plans and financial security for data centers
    Limitation
    A Pennsylvania example, not Iowa law or evidence that Peosta has adopted these protections.
  13. Local recordEvidence grade CAugust 2026
    Peosta Energy and Data Campus: discussion materials

    City of Peosta / project concept

    Scope
    August 2026 preliminary campus and on-site generation concept posted by the city
    Limitation
    Developer discussion estimates, not approved capacity, metered demand, an executed tenant lease or an independently verified operating plan.
  14. Official reportEvidence grade BJune 2026
    United States Data Center Energy Usage Report: 2025 Update

    Lawrence Berkeley National Laboratory

    Scope
    United States; history through 2024 and scenarios through 2030
    Limitation
    A bottom-up historical estimate and scenario forecast. The forecast does not model future grid-supply constraints or departures from announced demand.
  15. Official reportEvidence grade BDecember 2024
    2024 United States Data Center Energy Usage Report

    Lawrence Berkeley National Laboratory

    Scope
    United States; historical estimates through 2023 and scenarios through 2028
    Limitation
    Modeled national estimates with limited facility-level public data. Location-based emissions and indirect water do not include facility-specific contracts or behind-the-meter supply.
  16. Official reportEvidence grade BAugust 10, 2026
    Electricity Rate Designs for Large Loads: 2026 Update

    Lawrence Berkeley National Laboratory

    Scope
    55 U.S. large-load tariffs available through 2026
    Limitation
    The survey covers 55 published large-load tariffs. It cannot show that any one design will eliminate every cross-subsidy or forecast error.
  17. RegulationEvidence grade AJune 18, 2026
    FERC large-load integration show-cause orders

    Federal Energy Regulatory Commission

    Scope
    All six U.S. regional transmission organizations and independent system operators
    Limitation
    Show-cause orders begin a federal process; they do not establish a final national interconnection rule or determine one project's reliability effect.
  18. AuditEvidence grade BDecember 2024
    Data Centers in Virginia

    Virginia Joint Legislative Audit and Review Commission

    Scope
    Virginia, primarily FY2021–FY2023, with selected forecasts
    Limitation
    Virginia-specific. Several values are stakeholder estimates or model outputs, and future utility-cost scenarios are explicitly uncertain.