Skip to content

Are data centers draining community water supplies?

Some facilities consume meaningful water; others use little on site. Cooling system, climate, water source, peak-day demand, drought conditions, and the boundary of the number decide what the impact means.

Key facts, with scope and limits.

Direct site footprint66 billion L / year
Metric
Modeled water consumed on data-center sites
Scope
United States; primarily cooling infrastructure
Period
2023
Status
modeled
Indirect electricity footprintNearly 800 billion L / year
Metric
Modeled water consumed at electricity generators serving data-center load
Scope
United States electricity supply system; distinct from host-city utility demand
Period
2023
Status
modeled

Two water footprints in different places

The chart compares two distinct 2023 national footprints. On-site consumption occurs at data centers. Electricity-source consumption occurs across the power system. Adding them would overstate host-city demand.

LBNL modeled estimates, billion liters per year. The electricity-source figure is reported as nearly 800 billion liters and is plotted here as 800 for scale.

Two water footprints in different places data
CategoryModeled consumption (billion L/year)
On-site66 billion L/year
Electricity source800 billion L/year

mechanism diagram

In a typical evaporative configuration, where do makeup, recirculation, evaporation, and blowdown occur?

Heat moves from IT equipment through a facility cooling loop and heat exchanger to an evaporative cooling-tower loop. Recirculating water returns, makeup water enters, evaporation leaves to the atmosphere, and blowdown leaves for treatment or discharge.

  1. Heat starts hereIT equipmentServers reject heat
  2. Heat movesFacility cooling loopAir or liquid carries heat
  3. Systems meetChiller / heat exchangerHeat crosses into a condenser loop
On-site direct-water boundary

Evaporative cooling-tower loop

Water carries heat, then cycles back through the system.

Input · enters loop

Makeup water

New delivery replaces water that leaves the loop.

Return · stays in loop

Recirculation

Most loop water is used again rather than withdrawn again.

Output · consumed

Evaporation

Water transfers heat to the atmosphere.

Output · not evaporation

Blowdown

A smaller stream leaves for treatment or discharge.

A conceptual evaporative-cooling loop based on DOE federal data-center guidance and USGS water-use definitions. Makeup replaces evaporation and blowdown; actual designs and site water intensity vary.
Scope
Typical evaporative-cooling configuration for a federal data center; not all facilities
Period
Current terminology; DOE guidance published January 2019
Metric
Process relationships only; no facility volume or water-use efficiency value

LimitConceptual typical evaporative-cooling configuration. Actual facilities can use air cooling, dry coolers, economizers, direct liquid cooling, reclaimed water, or different loops. Climate, chemistry, and operating setpoints change the flows. This does not estimate a site's WUE or peak demand.

Use the national baseline to read the local record.

National baseline

Water withdrawal, consumption, delivery, and discharge are different quantities. LBNL's national model provides scale. Cooling design and geography create wide variation, and the indirect power-sector footprint occurs elsewhere.

Local case

National totals cannot answer whether a particular watershed or utility is constrained. A local assessment needs a full-build water balance, source by source, including the hottest day and the drought plan.

What the evidence supports.

Every data center consumes an enormous amount of water.
False: on-site consumption varies widely

Water use is not uniformly high. Evaporatively cooled sites can be significant consumers; air-cooled designs can have very low on-site consumption. LBNL modeled more than one million cooling-and-weather cases rather than one universal rate.

LBNL’s nearly 800 billion liters in 2023 came from host-city pipes.
False: that figure includes water used to generate electricity

The nearly 800-billion-liter estimate is not a host-city water demand figure. It covers consumption across the electricity supply system. LBNL's modeled direct on-site total was 66 billion liters in 2023.

Ask for these local records.

Without these inputs, a project-specific verdict is incomplete. Treat missing evidence as an open question.

  1. 01Potable, reclaimed, groundwater, and surface-water shares, with enforceable commitments
  2. 02Annual delivery, consumptive loss, discharge, and metered history kept as separate metrics
  3. 03Peak-day and peak-hour makeup demand under design weather
  4. 04Every campus phase and cooling mode, including commissioning and emergency operation
  5. 05Drought triggers, curtailment priority, backup mode, and the serving utility's capacity plan

Sources used on this page.

  1. Official reportGrade B
    2024 United States Data Center Energy Usage Report

    United States; historical estimates through 2023 and scenarios through 2028

    Modeled national estimates with limited facility-level public data. Location-based emissions and indirect water do not include facility-specific contracts or behind-the-meter supply.
  2. GuidanceGrade A
    Water-use terminology

    United States water-use accounting

    Defines accounting terms; it does not quantify data-center use or determine local scarcity.
  3. GuidanceGrade A
    Cooling Water Efficiency Opportunities for Federal Data Centers

    Cooling-water efficiency practices for federal data centers

    Federal-facility guidance. Technology savings and feasibility remain dependent on the site's climate, chemistry, and operating design.
  4. AuditGrade B
    Data Centers in Virginia

    Virginia, primarily FY2021–FY2023, with selected forecasts

    Virginia-specific. Several values are stakeholder estimates or model outputs, and future utility-cost scenarios are explicitly uncertain.
Browse the complete source library